Tiling

Tiling





In this task we were at the race corse tiling the shower room.
This task lasted about 2 weeks.

The tools we used were;

Adhesive spreader

Tile cutter

Pencil

Level

The materials we used was:

Groute

Adhesive

Tiles

Water


The P.P.E we used were:

Saftey boots

Hight vis

Gloves

overalls


Dado rail and skirting board

Dado and skirting board


In this task we were fitting the dado rail and skirting board.
This task lasted us 3 weeks .


The tools we used were:

Hammer

benched saw

coping saw

nail punch


The materials we used were:

Nails

Skirting board

Dado rail

The P.P.E we used were:

Saftey Boots

Goggles

Gloves

Overalls

Dust mask


Monday 3 June 2013

Gloss and emulsion paint

Gloss and emulsion





In this task we had to prepare to apply emulsion paint to the walls the paint colour we used was while and a barley mow  we were working on this task for 3/4 weeks.

The tools we used was:

paint brushes

50mm and 25mm,

sand paper,

scraper to apply filler when needed

rollers and pad

The materials we used was:

paint,

filler,

water.

The P.P.E were:

 saftey boots,

goggles

 overalls,

goggles,

dust mask. 



Plastering


In this task i had to plaster our bays this task lasted 4/6 weeks we were in groups of 3 to mix the plaster to the right setting we have 45 mins to aplly the plaster to te wall.

The tools we used was:

Plastering towel

Hawk

Trowel

Mixing stick

The materials we used was:

Plaster

Water

The P.P.E we used was:

Saftey boots

Goggles

Overalls

Gloves


Stud work

Stud work



In this task we had to make a z frame out of 2 by 4 millimetres this task lasted us 3/4 weeks.

The tools we used was:
 battery driver

 pencil,

 tape measure

 square

 step ups.

The  materials we used was:

 Philip head Screws

 wood,

nails

The P.P.E we used was:
saftey boots,

goggles,

 gloves.





Plasterboarding

Plasterboarding



In this task we were plaster boarding this task lasted us 3 weeek the sheet of the plasterboards were 2400mm by 100mm.


The tools we used were:
 Stanley knife

 Level

pencil

tape

 surform

battery driver

 step up

dust sheet

 broom

The materials were:

 dry wall screws

plasterboard

wood

skim tape,

The P.P.E we used was:

 saftey boots

 goggles

 gloves

 dust mask

Brick laying

Brick laying



In this task we were working by our self to build a pyramid. This task lasted 8 weeks.

We started with 5 bricks to make a small pyramid  as a practise test then we moved on to a large pyramid.

Then we build an old english bond wall for our exam.

The tools we used were:

 level

brick trowel,

brick guage

poitning trowel,

 bolster chisel,

Spot board,
the P.P.E was:

saftey boots
goggles